How long will my permit take to be issued?

The length of time it takes to get a building permit can vary depending on many factors such as project complexity and application completeness. No Plan Check permits are either processed as Auto Issue (e.g., water heaters, reroofs) or OTC (Over the Counter). Auto Issue permits are processed same day. OTC permits have a 3-5 days turnaround. Permits with Plan Check have a turnaround of 6-8 weeks.